The progress calculation is not calculating at all, even when you have half of the tasks completed. It is greyed out you can’t even change the progress percentage manually.
Page 1 / 1
Hi
Progress towards completion is calculated based on the project's Progress % or Calculated Progress %. You may choose which of these two fields is used under Tasks / Projects > Project Settings.
You can review the configuration by following our guide.
Additionally, if you still encounter issues, please don’t hesitate to reach us by submitting a ticket or coming on chat for live support.
Thank you!
Reply
Enter your E-mail address. We'll send you an e-mail with instructions to reset your password.