The progress calculation is not calculating at all, even when you have half of the tasks completed. It is greyed out you can’t even change the progress percentage manually. 

Hi @ElizabethM ,

 

Progress towards completion is calculated based on the project's Progress % or Calculated Progress %. You may choose which of these two fields is used under Tasks / Projects > Project Settings.

 

You can review the configuration by following our guide.

 

Additionally, if you still encounter issues, please don’t hesitate to reach us by submitting a ticket or coming on chat for live support.

 

Thank you!


Reply