Solved

Project progress calculation

  • 6 November 2023
  • 1 reply
  • 15 views

The progress calculation is not calculating at all, even when you have half of the tasks completed. It is greyed out you can’t even change the progress percentage manually. 

icon

Best answer by AlexanderChr 6 November 2023, 09:40

View original

1 reply

Userlevel 1
Badge +1

Hi @ElizabethM ,

 

Progress towards completion is calculated based on the project's Progress % or Calculated Progress %. You may choose which of these two fields is used under Tasks / Projects > Project Settings.

 

You can review the configuration by following our guide.

 

Additionally, if you still encounter issues, please don’t hesitate to reach us by submitting a ticket or coming on chat for live support.

 

Thank you!

Reply